Hello Bike Board (or, rather, previous members of the bike board),
As you can see below, our assistant city manager would like me to solicit feedback on repair stations included with the Hazel Ruby McQuain park renovations.
They are currently planning to install one near bike parking on the walnut landing. Originally they planned to install two - the other was to be installed near bike parking close to the will call office (old bus depot). See the attached drawings for contextual information.
Feedback please: 1) Are you okay with just one fix-it station? 2) If so, where would you like it to be located? Preferably this would be one of the two previously mentioned locations, but if you have strong opinions otherwise feel free to share them 3) If not, are you willing to spend monies in the escrow account slated for bike stuff around town to install the second?
Alternatively, if you are willing to spend monies (we have ~$10.5K in escrow), but don't see the need for two fix-it stations in such close proximity, you could voice an opinion to install one somewhere else in city limits. They generally run b/t $1K-$2K. I heard recently that one was supposed to be installed at the new White Park parking area trailhead, but I am unsure of where that currently stands.
Cheers, Drew
________________________________ From: Emily Muzzarelli emuzzarelli@morgantownwv.gov Sent: Wednesday, September 25, 2019 11:42 AM To: (John)Drew Gatlin jgatlin@morgantownwv.gov Subject: RE: HRM Bike Fix It Station
See attached.
Thank you,
Emily Muzzarelli, P.E.
Assistant City Manager 389 Spruce Street Morgantown, WV 26505 Office: (304) 284-7406 morgantownwv.gov [MORGANTOWN-WITH TEXT - Email]<morgantownwv.gov>
From: (John)Drew Gatlin jgatlin@morgantownwv.gov Sent: Tuesday, September 24, 2019 9:45 AM To: Emily Muzzarelli emuzzarelli@morgantownwv.gov Subject: Re: HRM Bike Fix It Station
Will do. Can you get me a shareable site plan that contains the original two locations with some contextual info?
I'll reiterate that I don't think bike board has seen these plans in any detail and that they may very well have not been aware that two fix-it stations were planned.
I'm guessing they will be happy with one, though I bet they wish it was closer to the rail-trail rather than down on the landing.
-Drew ________________________________ From: Emily Muzzarelli <emuzzarelli@morgantownwv.govmailto:emuzzarelli@morgantownwv.gov> Sent: Tuesday, September 24, 2019 9:22 AM To: (John)Drew Gatlin <jgatlin@morgantownwv.govmailto:jgatlin@morgantownwv.gov> Subject: HRM Bike Fix It Station
Drew,
Can you please discuss with the Bike Board…
For budget reasons, we had to remove 1 Bike Fix It Station from the design of HRM Park. There will still be one at the Walnut Street Landing Area. The one in the parking lot by the Depot has been removed.
Does the Bike Board feel that two are necessary? If so, does the Bike Board want to cover the cost of a second station? If so, I can get you a final cost.
Thank you,
Emily Muzzarelli, P.E.
Assistant City Manager
389 Spruce Street
Morgantown, WV 26505
Office: (304) 284-7406
morgantownwv.gov
[MORGANTOWN-WITH TEXT - Email]<morgantownwv.gov>
Hi all, I’m included but not a bike board member. Here are my two cents.
1) I am fine with one. 2) I hope this one goes near the depot which is next to the trail and near new restrooms etc.
MRTC will be ordering and putting same fix it stations (we had fundraising campaign for them) at Van Voorhis Trailhead, Star City Trailhead, Masontown Trailhead and Pricketts Fort Trailhead. I could see others being useful along the Deckers Creek Trail in city limits through Sabraton or near Marilla Park trail parking.
I believe Colin Dierman or BOPARC would be able to give an update on the one for White Park.
Cheers, Ella
Ella Belling Executive Director Mon River Trails Conservancy P.O. Box 282 Morgantown, WV 26507 http://montrails.org 304-692-6782
On Sep 25, 2019, at 11:53 AM, (John)Drew Gatlin via Bikeboard bikeboard@bikemorgantown.com wrote:
Hello Bike Board (or, rather, previous members of the bike board),
As you can see below, our assistant city manager would like me to solicit feedback on repair stations included with the Hazel Ruby McQuain park renovations.
They are currently planning to install one near bike parking on the walnut landing. Originally they planned to install two - the other was to be installed near bike parking close to the will call office (old bus depot). See the attached drawings for contextual information.
Feedback please:
- Are you okay with just one fix-it station?
- If so, where would you like it to be located? Preferably this would be one of the two previously mentioned locations, but if you have strong opinions otherwise feel free to share them
- If not, are you willing to spend monies in the escrow account slated for bike stuff around town to install the second?
Alternatively, if you are willing to spend monies (we have ~$10.5K in escrow), but don't see the need for two fix-it stations in such close proximity, you could voice an opinion to install one somewhere else in city limits. They generally run b/t $1K-$2K. I heard recently that one was supposed to be installed at the new White Park parking area trailhead, but I am unsure of where that currently stands.
Cheers, Drew
From: Emily Muzzarelli <emuzzarelli@morgantownwv.gov mailto:emuzzarelli@morgantownwv.gov> Sent: Wednesday, September 25, 2019 11:42 AM To: (John)Drew Gatlin <jgatlin@morgantownwv.gov mailto:jgatlin@morgantownwv.gov> Subject: RE: HRM Bike Fix It Station
See attached.
Thank you,
Emily Muzzarelli, P.E.
Assistant City Manager 389 Spruce Street Morgantown, WV 26505 Office: (304) 284-7406 morgantownwv.gov x-msg://100/morgantownwv.gov x-msg://100/morgantownwv.gov
From: (John)Drew Gatlin <jgatlin@morgantownwv.gov mailto:jgatlin@morgantownwv.gov> Sent: Tuesday, September 24, 2019 9:45 AM To: Emily Muzzarelli <emuzzarelli@morgantownwv.gov mailto:emuzzarelli@morgantownwv.gov> Subject: Re: HRM Bike Fix It Station
Will do. Can you get me a shareable site plan that contains the original two locations with some contextual info?
I'll reiterate that I don't think bike board has seen these plans in any detail and that they may very well have not been aware that two fix-it stations were planned.
I'm guessing they will be happy with one, though I bet they wish it was closer to the rail-trail rather than down on the landing.
-Drew From: Emily Muzzarelli <emuzzarelli@morgantownwv.gov mailto:emuzzarelli@morgantownwv.gov> Sent: Tuesday, September 24, 2019 9:22 AM To: (John)Drew Gatlin <jgatlin@morgantownwv.gov mailto:jgatlin@morgantownwv.gov> Subject: HRM Bike Fix It Station
Drew,
Can you please discuss with the Bike Board…
For budget reasons, we had to remove 1 Bike Fix It Station from the design of HRM Park. There will still be one at the Walnut Street Landing Area. The one in the parking lot by the Depot has been removed.
Does the Bike Board feel that two are necessary? If so, does the Bike Board want to cover the cost of a second station? If so, I can get you a final cost.
Thank you,
Emily Muzzarelli, P.E.
Assistant City Manager 389 Spruce Street Morgantown, WV 26505 Office: (304) 284-7406 morgantownwv.gov x-msg://100/morgantownwv.gov x-msg://100/morgantownwv.gov
Bikeboard mailing list Bikeboard@bikemorgantown.com mailto:Bikeboard@bikemorgantown.com http://wvcompletestreets.org/mailman/listinfo/bikeboard http://wvcompletestreets.org/mailman/listinfo/bikeboard
Geez, didn't see Ella's response but glad I didn't contradict :)Darn app settings messed me up.
Sent from Yahoo Mail on Android
On Wed, Sep 25, 2019 at 1:33 PM, Ella Belling via Bikeboardbikeboard@bikemorgantown.com wrote: _______________________________________________ Bikeboard mailing list Bikeboard@bikemorgantown.com http://wvcompletestreets.org/mailman/listinfo/bikeboard
My opinion-1 is fine, located at the old depot building, not by walnut. MRTC has helped raise funds & received donations for 4 others along the trail outside city limits, likely at Van Voorhis, Masontown, Star City & Pricketts Fort trailheads. We hope to have them in hand soon & installed before the snow flies. Good stuff!Christiaan Sent from Yahoo Mail on Android
On Wed, Sep 25, 2019 at 11:54 AM, Drew Gatlin via Bikeboardbikeboard@bikemorgantown.com wrote: #yiv9050339112 P {margin-top:0;margin-bottom:0;}Hello Bike Board (or, rather, previous members of the bike board), As you can see below, our assistant city manager would like me to solicit feedback on repair stations included with the Hazel Ruby McQuain park renovations. They are currently planning to install one near bike parking on the walnut landing. Originally they planned to install two - the other was to be installed near bike parking close to the will call office (old bus depot). See the attached drawings for contextual information. Feedback please:1) Are you okay with just one fix-it station?2) If so, where would you like it to be located? Preferably this would be one of the two previously mentioned locations, but if you have strong opinions otherwise feel free to share them3) If not, are you willing to spend monies in the escrow account slated for bike stuff around town to install the second? Alternatively, if you are willing to spend monies (we have ~$10.5K in escrow), but don't see the need for two fix-it stations in such close proximity, you could voice an opinion to install one somewhere else in city limits. They generally run b/t $1K-$2K. I heard recently that one was supposed to be installed at the new White Park parking area trailhead, but I am unsure of where that currently stands. Cheers,Drew From: Emily Muzzarelli emuzzarelli@morgantownwv.gov Sent: Wednesday, September 25, 2019 11:42 AM To: (John)Drew Gatlin jgatlin@morgantownwv.gov Subject: RE: HRM Bike Fix It Station See attached.
Thank you,
Emily Muzzarelli, P.E.
Assistant City Manager
389 Spruce Street
Morgantown, WV 26505
Office: (304) 284-7406
morgantownwv.gov
From: (John)Drew Gatlin jgatlin@morgantownwv.gov Sent: Tuesday, September 24, 2019 9:45 AM To: Emily Muzzarelli emuzzarelli@morgantownwv.gov Subject: Re: HRM Bike Fix It Station
Will do. Can you get me a shareable site plan that contains the original two locations with some contextual info?
I'll reiterate that I don't think bike board has seen these plans in any detail and that they may very well have not been aware that two fix-it stations were planned.
I'm guessing they will be happy with one, though I bet they wish it was closer to the rail-trail rather than down on the landing.
-Drew
From: Emily Muzzarelli emuzzarelli@morgantownwv.gov Sent: Tuesday, September 24, 2019 9:22 AM To: (John)Drew Gatlin jgatlin@morgantownwv.gov Subject: HRM Bike Fix It Station
Drew,
Can you please discuss with the Bike Board…
For budget reasons, we had to remove 1 Bike Fix It Station from the design of HRM Park. There will still be one at the Walnut Street Landing Area. The one in the parking lot by the Depot has been removed.
Does the Bike Board feel that two are necessary? If so, does the Bike Board want to cover the cost of a second station? If so, I can get you a final cost.
Thank you,
Emily Muzzarelli, P.E.
Assistant City Manager
389 Spruce Street
Morgantown, WV 26505
Office: (304) 284-7406
morgantownwv.gov
_______________________________________________ Bikeboard mailing list Bikeboard@bikemorgantown.com http://wvcompletestreets.org/mailman/listinfo/bikeboard
I agree with the one at the depot. Glad Ella got enough funds to put all 4 in. Soumds like good places for all 4.
Marilyn
Sent from my LG Mobile
------ Original message------
From: (John)Drew Gatlin via Bikeboard
Date: Wed, Sep 25, 2019 11:54 AM
To: Bike Board (bikeboard@bikemorgantown.com);
Cc: Emily Muzzarelli;
Subject:[Bikeboard] Fw: HRM Bike Fix It Station
Hello Bike Board (or, rather, previous members of the bike board),
As you can see below, our assistant city manager would like me to solicit feedback on repair stations included with the Hazel Ruby McQuain park renovations.
They are currently planning to install one near bike parking on the walnut landing. Originally they planned to install two - the other was to be installed near bike parking close to the will call office (old bus depot). See the attached drawings for contextual information.
Feedback please: 1) Are you okay with just one fix-it station? 2) If so, where would you like it to be located? Preferably this would be one of the two previously mentioned locations, but if you have strong opinions otherwise feel free to share them 3) If not, are you willing to spend monies in the escrow account slated for bike stuff around town to install the second?
Alternatively, if you are willing to spend monies (we have ~$10.5K in escrow), but don't see the need for two fix-it stations in such close proximity, you could voice an opinion to install one somewhere else in city limits. They generally run b/t $1K-$2K. I heard recently that one was supposed to be installed at the new White Park parking area trailhead, but I am unsure of where that currently stands.
Cheers, Drew
________________________________ From: Emily Muzzarelli emuzzarelli@morgantownwv.gov Sent: Wednesday, September 25, 2019 11:42 AM To: (John)Drew Gatlin jgatlin@morgantownwv.gov Subject: RE: HRM Bike Fix It Station
See attached.
Thank you,
Emily Muzzarelli, P.E.
Assistant City Manager 389 Spruce Street Morgantown, WV 26505 Office: (304) 284-7406 morgantownwv.gov [MORGANTOWN-WITH TEXT - Email]<morgantownwv.gov>
From: (John)Drew Gatlin jgatlin@morgantownwv.gov Sent: Tuesday, September 24, 2019 9:45 AM To: Emily Muzzarelli emuzzarelli@morgantownwv.gov Subject: Re: HRM Bike Fix It Station
Will do. Can you get me a shareable site plan that contains the original two locations with some contextual info?
I'll reiterate that I don't think bike board has seen these plans in any detail and that they may very well have not been aware that two fix-it stations were planned.
I'm guessing they will be happy with one, though I bet they wish it was closer to the rail-trail rather than down on the landing.
-Drew ________________________________ From: Emily Muzzarelli <emuzzarelli@morgantownwv.govmailto:emuzzarelli@morgantownwv.gov> Sent: Tuesday, September 24, 2019 9:22 AM To: (John)Drew Gatlin <jgatlin@morgantownwv.govmailto:jgatlin@morgantownwv.gov> Subject: HRM Bike Fix It Station
Drew,
Can you please discuss with the Bike Board…
For budget reasons, we had to remove 1 Bike Fix It Station from the design of HRM Park. There will still be one at the Walnut Street Landing Area. The one in the parking lot by the Depot has been removed.
Does the Bike Board feel that two are necessary? If so, does the Bike Board want to cover the cost of a second station? If so, I can get you a final cost.
Thank you,
Emily Muzzarelli, P.E.
Assistant City Manager
389 Spruce Street
Morgantown, WV 26505
Office: (304) 284-7406
morgantownwv.gov